Gradual increase in passenger train speeds
First and foremost, we would like to once again extend our sincere apologies for the inconvenience and concerns caused by this incident. We understand the impact it has had on your community and want to reassure you that public safety remains at the heart of our priorities. In a spirit of transparency and collaboration, we believe it is important to keep residents informed throughout the gradual return to normal railway operations.
Since the derailment, CN has completed extensive work to restore its railway infrastructure and strengthened its inspection measures. Approximately 2,400 feet (750 metres) of track have been rebuilt, more than 2,000 tonnes of crushed stone have been used to reinforce the track foundation, the track has been levelled, all railway ties have been replaced, and a new public grade crossing has been constructed.
Following several inspections, Transport Canada confirmed in a letter dated September 14, 2026, that the corrective measures promptly implemented by CN met the applicable requirements and that
the safety systems inspected were functioning as intended. This confirmation marks an important step toward the safe and gradual return to normal railway operations, and we wanted to share this
important update with you.
In this context, CN will gradually increase passenger train speeds (VIA Rail), currently limited to 10 mph (16 km/h), according to the following schedule:
- November 27, 2026: Speed increase to 30 mph (48 km/h);
- December 14, 2026: Speed increase to 50 mph (80 km/h);
- January 4, 2027: Speed increase to 75 mph (121 km/h), the maximum permitted speed.
In addition, restoration work in the area, including repairs to the bike path, is nearing completion. Once finalized, only tree planting will remain, which is scheduled for spring 2027.
For any questions or concerns, please contact CN’s Public Inquiry Line at 1-888-888-5909 or by email at CN Public Inquiry Line . To submit a claim, please contact General Claims Canada