The following is the proposed timeline for the development of the CN Calgary Logistics Park.
2010
April
- Public Open House
- Submission of Land Use Amendment applications to Rocky View County
May
- Completion of technical work to support the Regulatory Application
- Completion of engineering investigation and conceptual design
June
- Completion and submission of the Environmental Assessment
- Second Public Open House
July
- Application submission to the Canadian Transportation Agency (CTA)
December
- Anticipated approval for Land Use Amendment process by Rocky View County
- Anticipated project approval by the Canadian Transportation Agency
2011
- Pipeline Relocates
- Site Grading including Site Access and Drainage
- Utilities
- Building Foundation
- Road Improvements
2012
- Track Construction
- Intermodal Facility Paving
- Building Construction
- Power Distribution
- Lighting
- Road Construction
2013
- Completion of Remaining Work
- In Service